FOUR SEASON HOTELS-SOWWAH SQUARE
Location: Abu Dhabi
Client: Mubadala Development Company
Consultant: Serex International
Main Contractor:
Contract Date: 10-July-2010
Completion Date: 12-December-2010
Project Summary
Piling
Pile Diameter: 900mm – 1800mm
Pile Quantity: 319 nos.
Pile Length: 10.00m – 41.00m
Total Pile Length: 10,000m
Shoring
Shoring Type: Soldies piling wall
Shoring Length: 460rmt
Retaining Depth: 4.50m
Soil Anchors: -
Earth Works
Bulk Excavation: 27,000m3