Project Summary
Piling
Pile Diameter: 1200mm – 1500mm
Pile Quantity: 1,029 nos.
Pile Length: 24.0m – 52.5m
Total Pile Length: 43,000m
Shoring
Shoring Type: Secant Pile
Shoring Length: 465 rmt
Retaining Depth:18.00m
Excavation: 250,000 m3